In plain words
Virginia passed a statewide law on accessory dwelling units (ADUs) in April 2026. It does not start until July 1, 2027. An ADU is a small second home on the same lot as a house. Examples are a backyard cottage, a garage apartment or a basement unit with its own kitchen and bathroom.
Zoning is the set of local rules that says what you can build where. Today, each county, city and town decides on ADUs. Some approve them at the counter, some require a special public hearing, and some do not allow them.
From July 2027, areas zoned for single-family homes must allow an ADU, with one big exception explained below. The locality must issue an ADU permit if the plans meet the law's limits. The plans must also meet local building, water, sewer and safety codes. The ADU permit fee is capped at $500, plus normal building fees.
Localities can still set some rules. They can require the owner to live in the house or the ADU when applying. They can require rentals of at least 30 days and a parking space. They can cap the size, but the cap must be at least 500 square feet on most lots. A setback is the required gap between a building and the property line. The ADU's setback cannot be bigger than the house's.
Here is the big exception. A place that already had its own ADU ordinance (a local law) before January 1, 2026 keeps its own rules. That likely covers Fairfax, Arlington, Loudoun, Alexandria and Richmond.
Homeowner association rules and deed covenants still apply. A covenant is a private rule written into a property's deed. You can build only if local rules and your property allow it.
The rules at a glance
| State ADU law | Yes |
|---|---|
| Where the state rule applies | Single-family residential zoning districts in every Virginia county, city and town, starting July 1, 2027, except any locality that adopted an ADU ordinance before January 1, 2026 (those keep their own rules). Permits approved before July 1, 2027 are not affected. |
| Approved without a hearing? | Partly. Some ADUs or some places get staff approval; others can still need a hearing. |
| Kinds of ADU the state protects | internal, attached, detached |
| ADUs per lot | The law sets no number. ADUs become a permitted accessory use on single-family lots, and a locality may bar an ADU on a lot that already has more than one dwelling unit, so in practice expect 1 ADU per lot. A locality may also bar selling the ADU separately. |
| Owner living on site | Towns may require the owner to live on the property. |
| Parking | Localities may require dedicated parking for the ADU and may require replacement of any required parking for the main house that the ADU removes. (The introduced bill would have banned new parking requirements; the final law allows them.) |
| Size | No statewide maximum. A locality may cap ADU floor area, lot coverage and paved area, but the cap may not be smaller than 350 sq ft on lots under 2,500 sq ft or 500 sq ft on lots of 2,500 sq ft or more. |
| Lot size and setbacks | Side and rear setbacks for an ADU can be no larger than the smaller of the main house's setback or the accessory-structure setback. Height, setback, lot size, lot coverage and frontage rules cannot be stricter than those for a single-family home in the same zone. A locality may require the ADU to be within 500 feet of the main house. |
| Fees | ADU permit fee capped at $500, charged on top of normal building, inspection and site permit fees. Localities may not require public street improvements, except repairing a street damaged by the ADU's construction. |
| Short-term rentals | Localities may require that ADU rentals be for 30 consecutive days or longer. |
| Can towns opt out? | No |
What to do next
- Find out which government zones your land (county, independent city or town) and read its current ADU or accessory apartment rules.
- Ask the zoning office whether it adopted an ADU ordinance before January 1, 2026; if so, its own rules keep applying after July 1, 2027.
- Read your HOA covenants, condo documents and deed restrictions, because the state law does not override them.
- Check water, sewer or septic capacity, flood zone and any historic district limits early, since localities may still enforce them.
- If you plan to rent the unit, ask about minimum lease terms (often 30 days) and any owner-occupancy affidavit.
- If you want to build before July 2027, plan around your locality's current rules; the new section does not touch permits approved before that date.
What your town still decides
Until July 1, 2027, every Virginia county, city and town still sets its own ADU rules, and several (Fairfax County, Arlington, Alexandria, Loudoun, Richmond, Falls Church) already allow ADUs in some form, some by staff approval and some only after a special permit hearing. After that date, localities with no pre-2026 ADU ordinance must follow the state section. The final law exempts any locality that adopted an ADU ordinance before January 1, 2026, with no condition on how permissive that ordinance is (the introduced bill only exempted ordinances that did not treat ADUs as a special use). There is no new opt-out window. Localities may still require owner occupancy at the time of application only, enforce building codes, and apply water, sewer, septic, flood zone, stormwater, historic district and military airfield (AICUZ) limits. Private covenants, condo instruments and property owners' association rules are not overridden. A separate 2025 law (2025 Acts ch. 570) let comprehensive plans plan for tiny homes and ADUs, but it required nothing, and the current online Code text no longer shows that wording.
Examples of local rules
- Fairfax County: Calls them accessory living units (ALUs). Interior units get an administrative permit; detached units need a special permit from the Board of Zoning Appeals (a public hearing) and a lot of at least 2 acres. Owner must live on site, max 2 bedrooms and 2 people, interior units up to 800 sq ft or 40% of the house, detached up to 1,200 sq ft, one extra parking space, permit renewals required. Staff proposed loosening these rules in December 2025, with hearings possible by the end of 2026. Source
- Arlington County: One accessory dwelling per lot, inside the house, attached, or in a detached building, approved administratively by the Zoning Administrator (about 30 days). Owner must live in the house or the unit, max 3 occupants, size capped by house size (for example 35% of combined floor area up to 750 sq ft), one off-street space with exceptions, and setback rules for detached buildings built after May 2019. Source
- City of Richmond: Since a September 25, 2023 ordinance, one ADU is allowed with a single-family home in every residential zoning district. It may be up to one-third of the main house's floor area or 500 sq ft, whichever is greater, and must meet the zone's normal setbacks, lot coverage and height limits. Source
- Loudoun County: Per Fairfax County's December 2025 comparison: interior and detached units allowed by right, no owner-occupancy rule, one parking space per unit, size limits from 1,200 to 2,500 sq ft or 50-70% of the main house, and no minimum lot size for detached units. Source
- City of Alexandria: Per Fairfax County's December 2025 comparison: interior and detached units approved administratively, allowed with single-family, two-family and townhouse homes, owner-occupied when the permit is issued, max 3 occupants, no parking requirement, detached units 1 to 5 feet from side and rear lines. Source
What we’re still confirming
- Localities that adopted an ADU ordinance before January 1, 2026 are exempt from the new state requirement, and there's no published list of them; ask yours.
- Whether an exempt locality loses that status if it changes its ADU ordinance later isn't settled.
Laws, bills and citations
The laws behind this (3)
- Development and use of accessory dwelling units (SB 531) (Va. Code § 15.2-2292.4 (effective July 1, 2027), enacted by SB 531 (2026), 2026 Acts of Assembly ch. 895. The act numbered the new section § 15.2-2292.3; it is codified as § 15.2-2292.4 because 2026 Acts ch. 406 (HB 594) also created a § 15.2-2292.3., signed April 13, 2026, in effect July 1, 2027). From July 1, 2027, zoning for single-family districts is treated as allowing an attached or detached ADU as an accessory use. The locality must issue an ADU permit (fee capped at $500) when the plans meet the section's limits and local building, utility, flood and historic rules. Any locality that adopted its own ADU ordinance before January 1, 2026 is exempt, and HOA covenants and condo documents still control. Read it
- Comprehensive plans may plan for tiny homes and ADUs (permissive only) (2025 Acts of Assembly ch. 570 (HB 2533), amending Va. Code § 15.2-2223(C)(1), signed March 24, 2025, in effect July 1, 2025). Let, but did not require, a locality's comprehensive plan (its long-range land-use plan) designate areas for tiny homes (400 sq ft or less) and ADUs, and defined an ADU as a unit inside, attached to or detached from a single-family home. It required no locality to allow ADUs. A 2026 amendment to the same section (2026 Acts ch. 375, HB 257) reenacted it without this wording, and the current online Code does not show it. Read it
- Temporary family health care structures (Va. Code § 15.2-2292.1 (2010 Acts ch. 296; amended 2013 Acts ch. 178), signed January 1, 2010, in effect July 1, 2010). Localities must treat one small temporary structure (up to 300 gross sq ft) as a permitted accessory use on single-family lots when a family caregiver or guardian uses it to care for a physically or mentally impaired person. No special use permit is allowed, the permit fee is capped at $100, and the structure must be removed within 60 days after it was last occupied by that person. Read it
Proposed and failed bills (5). None of these is law.
- HB 611 (2026): pending as of October 3, 2026. House companion to SB 531 from Del. Laura Jane Cohen, with a $500 permit fee cap and a ban on most new parking requirements. The House Counties, Cities and Towns Committee continued it to the 2027 session by voice vote on January 30, 2026, so it is technically still alive, though SB 531 already enacted most of its substance. Bill page
- HB 1832 (2025): died as of October 3, 2026. Statewide ADU mandate with a $500 permit fee cap that barred parking rules except in single-family zones with lots under 10,000 sq ft. A House subcommittee folded it into HB 2533 on January 23, 2025, and it was left in the House Counties, Cities and Towns Committee on February 4, 2025. HB 2533 became law only as a planning bill (2025 Acts ch. 570). Bill page
- SB 932 (2025): died as of October 3, 2026. Introduced by Sen. Salim as a statewide ADU mandate. On January 27, 2025 the Senate Local Government Committee replaced it with a substitute that only let comprehensive plans include tiny homes and ADUs (folding in SB 1256). That version passed the Senate 30-10 on January 30, cleared the House Counties, Cities and Towns Committee 21-0 on February 7, and was left in the House Rules Committee on February 18, 2025. Bill page
- SB 304 (2024, carried to 2025): died as of October 3, 2026. Would have required localities to allow ADUs in single-family zones, with a $250 permit fee cap and setback limits. Passed the Senate 22-18 on February 9, 2024. The House Counties, Cities and Towns Committee continued it to 2025 on February 23, 2024, then left it in committee on November 18, 2024. Bill page
- HB 900 (2024, carried to 2025): died as of October 3, 2026. House version from Del. Srinivasan with a $100 permit fee cap and a ban on dedicated-parking rules. On February 2, 2024 the committee continued it to 2025 with a substitute that raised the fee cap to $250 and exempted localities whose pre-2024 ordinance already allowed ADUs by right without parking rules. It was left in committee on November 18, 2024. Bill page
Sources
- Va. Code § 15.2-2292.4 (effective July 1, 2027), enacted by SB 531 (2026), 2026 Acts of Assembly ch. 895. The act numbered the new section § 15.2-2292.3; it is codified as § 15.2-2292.4 because 2026 Acts ch. 406 (HB 594) also created a § 15.2-2292.3. · official source
- 2025 Acts of Assembly ch. 570 (HB 2533), amending Va. Code § 15.2-2223(C)(1) · official source
- Va. Code § 15.2-2292.1 (2010 Acts ch. 296; amended 2013 Acts ch. 178) · official source
- 2026 Acts of Assembly, Chapter 895 (SB 531), approved April 13, 2026 (copy posted by the Town of Irvington) · official source · checked 2026-10-03
- SB 531 as introduced, 2026 Session (copy posted by the Town of Irvington) · official source · checked 2026-10-03
- Virginia LIS bill page, SB 531 (2026 Regular Session) · official source · checked 2026-10-03
- Virginia LIS bill page, SB 304 (2024 Session) · official source · checked 2026-10-03
- Virginia LIS bill page, HB 900 (2024 Session) · official source · checked 2026-10-03
- Virginia LIS bill page, SB 932 (2025) · official source · checked 2026-10-03
- BillTrack50, VA SB 932 (2025) status · checked 2026-10-03
- VACo, Action Item: Oppose Bill to Make ADUs a By-Right Use (SB 932, 2025) · checked 2026-10-03
- Fairfax County, Accessory Living Units: Background Information and Preliminary Concepts (Dec 2, 2025), with nearby-jurisdiction comparison · official source · checked 2026-10-03
- Arlington County, Accessory Dwelling Permit · official source · checked 2026-10-03
- City of Richmond, Accessory Dwelling Units · official source · checked 2026-10-03
- Virginia Housing Commission, Accessory Dwelling Units Introductory Brief · official source · checked 2026-10-03
- Virginia DHCD, State of the Market and Local Policy: ADUs in the Commonwealth of Virginia (RD629, Nov 2021) · official source · checked 2026-10-03
- VACo, Senate Passes Bill to Make ADUs a By-Right Use (SB 304, 2024) · checked 2026-10-03
- HousingForward Virginia, Virginia's 2026 General Assembly Housing Updates · checked 2026-10-03
- Virginia LIS, 2026 Acts of Assembly ch. 895 (SB 531) official chapter text · official source · checked 2026-10-03
- Virginia LIS bill page, HB 611 (2026), continued to 2027 · official source · checked 2026-10-03
- Virginia LIS bill page, HB 1832 (2025) · official source · checked 2026-10-03
- Code of Virginia § 15.2-2223, Comprehensive plan (current text and history line) · official source · checked 2026-10-03
- Virginia LIS, 2026 Acts of Assembly ch. 375 (HB 257) chapter text · official source · checked 2026-10-03
- Code of Virginia § 15.2-2292.3, Expedited approval for certain affordable housing developments (2026 c. 406) · official source · checked 2026-10-03
This is general information, not legal advice. Your town, village, city or county decides what can be built on your property. If something here looks out of date, email the team.